On June 8th, staff from multiple area municipalities – including the City of Edmonds – met with Snohomish County and the Overlays contractor for a pre-construction conference.  During the meeting, the contractor provided a schedule for the 2016 Overlay Program.

The schedule currently shows the contractor moving into Edmonds the week of June 20th to construct curb ramps at various locations in advance of the overlays.

The contractor plans to begin grinding and paving operations in Edmonds on July 5th and work in Edmonds is expected to continue until July 22nd.

All roadway construction operations are weather-dependent, but this is especially true of paving so be sure to check back often for updates.