Since our last update, the contractor has made some substantial progress and is looking to wrap up over the next couple of weeks.

This week, the contractor completed grinding operations on 96th St, 224th St and 72nd Ave. They expect to pave these streets next week.

100th Ave and 104th Ave should see grinding operations begin today, Friday, July 22nd. 100th will be paved later that week but 104th will have to hold off for some utility work to complete.

The contractor currently expects to begin grinding on Walnut St and 9th Ave N Monday, July 25th and pave these areas Wednesday, July 27th. This work will be very disruptive to Edmonds motorists so motorists should be aware of this work and avoid driving in these areas.

Railroad Ave has been put off until later this summer as we are waiting for some utility work to wrap up before paving that road.

We’ll do our best to keep you updated so please check back often!