The City of Edmonds waterline improvement projects propose to replace existing water main with new 4-inch, 6-inch, and 8-inch ductile iron water main and appurtenances including, but not limited to, fire hydrants, isolation valves, tie-in connections and water services.
Schedules provided herein are for reference only and are subject to change.
City of Edmonds 2013 Waterline Replacement Project
|
|||||
|
Timeline |
Location |
Type of Work |
Status |
||
| May 2013 | Maple 5th to 7th | Waterline install | In Progress | ||
| May/Early June 2013 | Spruce 7th to 96th & Spruce Pl | Waterline install | Not yet Started |
||
| June 2013 | Maple 5th to 7th | Asphalt Trench Patch | Not yet started |
||
| June 2013 | Spruce 7th to 96th & Spruce Pl | Asphalt Trench Patch | Not yet started |
||
| July 2013 | OVD & 76th | Waterline install | Not yet started | ||
| July 2013 | 175th Pl | Waterline install | Not yet started | ||
| Late July/Early Aug 2013 | 76th & Braemar Dr | Waterline install | Not yet started | ||
| August 2013 |
OVD & 76th | Asphalt Trench Patch | Not yet started | ||
| August 2013 | 175th Pl | Asphalt Trench Patch |
Not yet started | ||
| August 2013 | 76th & Braemar Dr. | Asphalt Trench Patch | Not yet started | ||
| September 2013 | 2nd Ave south of Pine |
Waterline install |
Not yet started |
||
| September 2013 | Elm between 2nd & 3rd | Waterline install | Not yet started | ||
|
September 2013 |
2nd north of Elm |
Waterline install
|
Not yet started | ||
| September 2013 |
Pioneer Way |
Waterline install
|
|
|
Not yet started |
| September 2013 | 2nd Ave south of Pine |
Asphalt Trench Patch
|
Not yet started | ||
| September 2013 | Elm between 2nd & 3rd | Asphalt Trench Patch | Not yet started | ||
|
September 2013 |
2nd north of Elm |
Asphalt Trench patch |
Not yet started | ||
| September 2013 |
Pioneer Way |
Asphalt Trench patch |
Not yet started | ||
|
|
|
|
|||
|
|
|||||
|
|
|||||
|
|
|||||