The challenging seawall portion of the Waterfront Redevelopment Project is nearing completion. Sheet piles have been driven, the concrete seawall, ramp and beach stairs have been poured, the original timber bulkhead has been removed and boulders, logs and beach sand have been placed. The remaining elements of the project include concrete sidewalks, an asphalt parking lot, various site amenities, artwork, landscaping and irrigation. The current schedule shows project completion by November 20th.