Dayton Street Utility Improvements

Project Limits

WHAT’S HAPPENING NOW?

One-way traffic on Dayton St will now travel westbound
Dayton St will continue to be one-way between 3rd Ave and 5th Ave, but the direction of traffic has been reversed. Traffic is now traveling westbound toward the waterfront while crews replace utilities on the other side of Dayton St.

The 4th Ave and Dayton St intersection will be closed August 20-21
During this closure:
 ·   Through traffic will be restricted
 ·   Access to businesses, driveways, and parking lots will be maintained
 ·   The sidewalks at the 4th Ave and Dayton St intersection will be closed;   
pedestrian detours will be in place

Looking ahead:
·    
The 5th Ave and Dayton St intersection will be closed for construction August 26-29. Please stay tuned for additional details next week

Thank you for your continued patience as we make progress replacing the aging and undersized utilities.

Intermittent work in the alley between 4th Ave and 5th Ave through mid August

Work will resume in the alley between 4th and 5th Ave. Crews anticipate completing work as soon as the week of August 19.  During this work: 

·        Local access to the alley will be maintained from both the north and south

·        Access to driveways and parking lots will be maintained

·        There may be some access delays as crews direct traffic through the work area

 

Community Transit buses will be running on alternate routes around work zones. Please visit Community Transit’s website for current rider alerts and routes: https://www.communitytransit.org/alert

Stay Informed on Project Updates

arrow b  Please stay tuned to this website for regular updates. We will be sharing project updates via email. To sign up for regular updates, or if you have questions or comments, email us at daytonproject@edmondswa.gov

arrow b  Check out our live feed of the construction site at: https://www.senserasystems.com/public/project/DaytonStProjec

arrow b  You can also follow project progress on Twitter at @DaytonStProject. 

Phase 1 (May-October 2019) and Phase 2 (2020)

Phase 1 of construction (Dayton Street from 3rd Ave S to 5th Ave S) will begin on May 13, 2019 and is anticipated to be completed in Fall 2019. Work during this phase will occur mostly between 3rd Ave S and 5th Ave S. Some sewer pipe rehabilitation work between 6th and 9th may be part of phase 1.

Traffic and pedestrian impacts

arrow b   One lane of traffic, either eastbound or westbound, will be maintained on Dayton St during most of construction.  Traffic control will be present ot direct people through the work area during construction.

arrow b   Parking will be restricted in the work area

arrow b   To provide safe working spaces for construction crews, there may be temporary intersection and/or block closures lasting for 1 to 3 days. We will notify businesses and neighbors ahead of these closures

arrow b   Sidewalks and driveways will remain open except for short durations to maintain safety throughout the corridor

 
Phase 2 of construction  (Dayton Street from 5th Ave S to 9th Ave S) will begin as early as Spring 2020 and last into Fall 2020

Project Description:

The Dayton Street Utility Improvements Project will replace aging and undersized utilities along Dayton Street from 3rd Ave S to 9th Ave S. Improvements will include:
    • Adding stormwater pipe capacity to reduce flooding in downtown during heavy rainstorms

    • Replacing sewer and potable water pipes that are nearing the end of their lifespan

    • Upgrading curb ramps to be ADA-accessible at the intersections of Dayton Street and 6th, 7th, 8th, and 9th Avenues

    • Adding a sidewalk along the south side of Dayton Street from 7th to 8th Avenues

Estimated Schedule:

  • Design was completed at the end of 2018

  • Phase 1 (3rd Ave S to 5th Ave S) construction will begin in May 2019

  • Crews do not plan to work between October 2019 and March 2020 over the holiday season

  • Construction will be divided into two phases. The second phase of construction (5th Ave S to 9th Ave S) is expected to start as early as Spring 2020 and last into Fall 2020

Scope:

Replace and upsize existing utilities on Dayton Street from 3rd to 9th Avenue. Improvements will include:

  • Replacing 3200 feet of stormwater pipe

  • Replacing 3800 feet of potable water pipe

  • Replacing 4300 feet of sanitary sewer pipe

  • New pavement on Dayton Street throughout the project limits

  • Constructing a new sidewalk on the south side of Dayton between 7th 
    and 8th Avenues

  • Constructing ADA-accessible pedestrian curb ramps

  • Revise sidewalks and intersections at Dayton St and 6th, 7th, and 8th, and 9th Avenues

Cost:

 ·  Construction costs estimated to be $7 million.

Utility Section Near 5th & Dayton

Cover

CLICK IMAGE TO ENLARGE

Schematic Utility Replacement Design

Dayton scroll plot

Dayton Street Project Contact

Construction Management Team
daytonproject@edmondswa.gov
425-771-0220

Follow us on Twitter at:
https://twitter.com/DaytonStProject

Check out our live stream at:
View Livestream

Public Works Engineering Division
City Hall - Second Floor
121 5th Ave N
Edmonds, WA 98020

Phone: (425) 771-0220
Fax: (425) 672-5750
engineering@edmondswa.gov

Public Hours:
8:00am to 4:30pm - M, T, Th, F
Wed 8:30am to Noon

Closed Weekends and Holidays

Engineering Capital Project Staff
Engineering Development Staff