City Walkway Improvements

Vicinity Map Madrona Walkway crop

Welcome to the City of Edmonds Sidewalk Project webpage.  Significant traffic delays are often experienced during porject construction, so be sure to check back for updates!

Walkway Projects

Madrona School Sidewalk Project

The Madrona School Sidewalk is the last of three Safe Routes to School grants won by the City of Edmonds during the 2013 grant cycle.  This project will install a sidewalk on the south side of 236th St SW from the Madrona School to Edmonds Way. Associated improvements include installation of stormwater pipe, signal improvements at the intersection of Edmonds Way and 236th St SW, and a minor widening of 236th St SW.

Bids were received on September 15th and a contract in the amount of approximately $573,000 was awarded to Welwest Construction on September 27th.

There will be significant traffic delays at times during the project construction so be sure to check back for updates!


Madrona Walkway Update - December 1, 2016

236th St SW will be closed between Edmonds Way and the Madrona School the week of December 5th.

Over the past few weeks, crews have been working on 236th St SW between Edmonds Way and the Madrona School.

Construction of 236th St SW has reached a point where the street will need to be closed to through traffic. The street will be closed on Monday, Dec 5th and should re-open to traffic on Friday, Dec 9th.

During this time, anyone accessing the school will be required to avoid 236th St SW entirely by approaching the school from a different direction. The school can be accessed from the north by 232nd St SW. Detour signs placed by the contractor will help you navigate this area.

We appreciate your continued patience as we work to improve 236th St SW.


Madrona Walkway Update – October 31, 2016

Our original schedule on the Madrona job had to get pushed back due to some paperwork issues but we’ve got our paperwork clear and we’re ready to hit the site!  The contractor will begin moving onto the site this Wednesday, November 2 and construction will be in full swing by Monday, November 7th.

This project is expected to take about 2 months to complete but a weather suspension is possible as winter draws closer.

Please take alternate routes whenever possible and – if you must drive through the work zone – be sure to plan additional time and be considerate of our workers’ safety.

Walkway Improvement Contact

Ryan Hague
Captial Projects Manager
425-771-0220 x1347
ryan.hague@edmondswa.gov

Rob English, PE
City Engineer
425-771-0220 x1327
robert.english@edmondswa.gov

Public Works Engineering Division
City Hall - Second Floor
121 5th Ave N
Edmonds, WA 98020

Phone: (425) 771-0220
Fax: (425) 672-5750
engineering@edmondswa.gov

Public Hours:
8:00am to 4:30pm - M, T, Th, F
Wed 8:30am to Noon

Closed Weekends and Holidays

Engineering Capital Project Staff
Engineering Development Staff